Wednesday, April 22, 2009 @ 3:03 PM
4/21/09 Outside grading and land balancing taking place
4/20/09 Trim work delivered and finish carpenters start installing cabinets
4/17/09 Cabinets delivered & Septic system installed
4/16/09 Ceramic tile delivered and prep work begins.
Well drilled and hooked up to house
4/15/09 All interior walls were primed and ceilings received final painting
From 3/30 thru 4/10/09 Drywall hanging and finishing as well as outside work was competed
3/30/09 Completed rough electrical and had mechanical, electrical, insulation and rough framing inspection...all ready for drywall
3/27/09 PM...Mark and the crew showed up and installed all of the windows, carefully sealed all the sills with water proofing material, flashed the exterior of all and checked for proper operation.
Week of 3/23 thru 3/27/09 This week consisted of all the electrical wiring, heating trunk lines, installing the HRV air exchanger and two fireplace plus venting. Inspections for rough Heating, Electrical, Fireplaces and gas line pressure test scheduled for Mon 3/30. Drywall is scheduled for 4/1/09.
3/21/09 Drywall being delivered and being hung beginning today- 26 working days have gone by since we started excavation and we are ready for drywall........progress moves on.